SLO@CAMBRIDGE UNITED HELPING SUPPORTERS
  • Hello
  • Matchday News
  • Matchday Info
  • SLO Page
  • Away Travel
    • AWAY TRAVEL INFORMATION
    • Young Persons Away Travel
  • Shop
  • CUFCLottery
    • Visit the lottery website
    • CUFCLottery sign up
    • CUFC Historic Lottery Winning Numbers
  • Fans Page Links
    • 100yearsofcoconuts
    • Amber Belles
    • Amber & Proud
    • Cambridge United
    • Cambridge United Supporters Club
    • Cambridge United Womens Team
    • CU Community Trust
    • CUFC Shop
    • Cambridge Fans United
    • CUSP
    • The Offside Trust
    • Under The Abbey Stand
    • Wellbeing

Ground Work some of the questions we have been asked

20/8/2018

0 Comments

 
Picture
Some Questions Answered Part 1

We have been asked some questions concerning the work being done around the ground during the past few months- Please see below for some of the answers and we will attempt to answer some more during the next week  –

Why do we water the pitch on match days?

 The Abbey Stadium pitch is a fibre sand construction and therefore there are several reasons for watering the pitch – the first is to ensure the moisture levels are kept up to the fibre sand manufacturers required levels. This helps provide the grass to root within the fibres.

 The moisture levels can fall due to several reasons temperature, wind and when the pitch is being played on. The surface takes up to 72 hours of moisture preparation before each fixture played on the pitch

The second reason is that coaches will want the pitch to play in a certain way. Some will want the ball to move quickly across the surface and others not.

This will also determine the length of that the grass is cut at. There is a minimum height suggested and different sports will require different lengths for example Rugby and football have longer grass than hockey .

How much is all the paint costing?
                           

The white paint around the ground was purchased via the sponsorship provided through a national company last season which enabled us buy some paint, paint brushes, rollers and other DIY materials used to do the external painting and the main stand hall way

The amber paint was purchased by the CUFCLottery run by CFU and through the kind donations of individuals and a local building supplier.

The only paint that the club has purchased is specialist paint ie Hammerite required for the bridges by the Habbin Stand and the safety barriers around the ground.

Additional paint brushes, rollers and paint have been supplied by the volunteers themselves.

Why is the painting being done?

There are two reasons for the painting being done around the ground. The main one is maintenance and the second is too provide club identity.

When the stadium inspection was carried out it highlighted the need for the walls which were painted white to be re-done and this is also part of the summer maintenance work schedule. The paint will protect the brickwork from frost and weathering during the winter. The work has been done annually, however this year we have tried to highlight the work being done. The Amber has been added to provide club identity which is an area that was highlighted in the survey replies over the past few years and particularly the lack of it. We have also added photos and pictures around to help do the same.

What work was done on the Habbin Bridge?

There are three bridges behind the Habbin Stand enabling supporters to enter and exit the ground.
 
The stadium maintenance report requested the painting of the Habbin South and middle bridges to be painted before the season began. This work will prevent the bridges from rusting and needing to be replaced in the future.
 
The third bridge was highlighted for repair at a future point several years ago when the middle one
was replaced. It has been manged through remedial work each summer. However, following the snow and cold weather last winter the concrete surface was damaged beyond repair. A new steel frame has been placed across the brook and concrete added. The tarmac slope is to reduce the need for any steps had this work not been undertaken the capacity of the Habbin North terrace would have been effected
 
Why was work being done on the South Stand?

The reservoir that manages the water being released from the roof was highlighted to be an area of concern. When it rains the amount of water coming from the roof is considerable and needs to be released slowly into the drainage systems at a level that is managed.

If the work had not been done it would have resulted in the closure of the stand until corrected.

The work was required to clean the guttering out. More than twenty dustbin bag of debris was removed. A new liner was then laid in the reservoir.

Because the work was at high level a cherry picker lift was required and the area around the working area closed to the public.
0 Comments

Your comment will be posted after it is approved.


Leave a Reply.

    Archives

    April 2022
    March 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015

    Categories

    All
    Abbey Stadium
    Abbey Stadium Redevelopment
    Alan Burge
    Cambridge Fans United
    Cambridge United
    Cambridge United Club Chaplain
    Cambridge United Community
    Cambridge United Womens Team
    CFU News
    Coconuts
    CUFC
    CUFCLottery
    CUFC Lottery
    David Burkett
    Diary
    EFL
    Ex Players
    Face In The Crowd
    Foodbank
    Football
    Football General
    Groundhoppers
    Ifollow
    Leo Orobor
    Man Of The Match
    Match Report
    Non-League
    Season Ticket
    Supporters
    Supporters Mental Health Liaison Office
    UK Parliament
    You Are Never Alone
    Your Are Never Alone

    RSS Feed

Picture
All Content on this Website remains the property and copyright of Dave Matthews-Jones and may not be reproduced or used without written permission.
​

Thanks are given to Cambridge United Football Club who have kindly given their permission to use their images and photographs on this site.

See our Privacy Policy.
Picture
  • Hello
  • Matchday News
  • Matchday Info
  • SLO Page
  • Away Travel
    • AWAY TRAVEL INFORMATION
    • Young Persons Away Travel
  • Shop
  • CUFCLottery
    • Visit the lottery website
    • CUFCLottery sign up
    • CUFC Historic Lottery Winning Numbers
  • Fans Page Links
    • 100yearsofcoconuts
    • Amber Belles
    • Amber & Proud
    • Cambridge United
    • Cambridge United Supporters Club
    • Cambridge United Womens Team
    • CU Community Trust
    • CUFC Shop
    • Cambridge Fans United
    • CUSP
    • The Offside Trust
    • Under The Abbey Stand
    • Wellbeing